Route 205 in Tracy Bridge Widening
Located in Tracy, CA along Rte. 205 from Corral Hollow Road to McArthur Blvd, this project consists of a Northbound Precast Box Grider Widening at Corral Hollow Road (70 CY of Concrete), a Southbound Cast In Place Box Girder Widening at Sugar Spur (Spanning over active Railroad Tracks and Canals) that includes Cast-In-Drilled-Hole Piling and Crash Walls (360 CY of Concrete), and two separate Retaining Walls and a Barrier Slab (Over 950 CY Combined. Bridgeway’s scope of work is scheduled to begin April 2023 and completed by early 2024.